+I have organized this evaluation into 4 sections.  The first section
+lists the work remaining to be done as a collection of tasks, with an
+assigned person and an amount of time.  In the second section, I list
+code milestones, with a summary of the related tasks.  These are
+labeled as 'ipp 2.7', etc, but we may opt not to make an official
+release of the software suite at these times: the additional support
+load is not justified.  In the third section, I give a list of
+sequential Pre-ORR data analysis milestones.  In the fourth section, I
+give a schedule, primarily detailing the coding tasks, but with the
+data analysis goals in [].
+
+----------------------------------------------------------------------------------
+
+IPP Pending Tasks
+
+Build / Config / PSLib 
+
+ * IPP 2.6 release
+ - PAP : 0.5 day
+
+Data Management
+
+ * finish 'cleanup' analysis for all stages
+ - EAM : 1 days  (ipp 2.7)
+
+ * output config files / verfy re-run
+ - PAP : 2 days  (ipp 2.7)
+
+ * 'update' analysis code for chip stage
+ - EAM : 2 days  (ipp 2.7)
+
+ * 'update' analysis for other stages
+ - EAM : 2 days  (ipp 2.7)
+
+Detrend Construction Software
+ 
+ * ppMerge threading
+ - EAM : 1 day (ipp 2.7)
+
+ * correct detrend normalization bug
+ - EAM : 0.25 day  (ipp 2.7)
+
+ * full-featured detrend construction simtest suite
+ - PAP : 1 day  (ipp 2.8)
+ 
+ * flat-field correction simtest suite
+ - JHU : 1 day  (ipp 2.8)
+ 
+ * flat-field correction demonstration with Megacam data
+ - JHU : 3 days (2 of background)
+ 
+ * flat-field correction demonstration with GPC1 data
+ - EAM / JHU : 3 days (2 of background) 
+
+  * Determine & Apply OT shifts
+  - PAP : 3 days (ipp 2.9) [requires complete OT data from GPC1]
+
+Single Science Image Analysis
+
+ * measure photmetry zero point in psastro
+ - EAM : 0.5 day (ipp 2.7)
+
+ * psphot threading
+ - EAM : 3 days (ipp 2.7)
+
+ * ongoing psphot shakeout
+ - EAM : 5 days (ipp 2.8)
+
+ * threading for ppImage (ex. psphot)
+ - EAM : 0.5 days (ipp 2.7)
+
+ * simtest demo of fake sources and forced photometry
+ - PAP : 2 days (ipp 2.8)
+
+ * generate summit Q/A feedback
+ - WS  : 3 days (ipp 2.9)
+
+Image Combinations
+
+ * ppStack threading
+ - PAP : 2 days (ipp 2.7)
+
+ * ppSub threading
+ - PAP : 2 days (ipp 2.7)
+
+ * Magic integration
+   * ippTasks (0.5 day)
+   * ippScipts (0.5 day)
+ - PAP : 1 day (ipp 2.7)
+
+ * Magic GPC1 testing 
+ - PAP : 5 days
+ 
+ * stack extended source photometry
+ - EAM : 5 days
+
+Calibration
+
+ * finish outlier flagging in relphot
+ - EAM : 2 days (ipp 2.9)
+
+ * 2D color-correction model (relphot)
+ - EAM : 3 days (ipp 2.9)
+
+ * finish absphot
+ - EAM : 3 days (ipp 2.9)
+
+Postage Stamp Server
+
+ * detectability analysis tool (image, RA, DEC -> psf Q factor)
+ - EAM : 0.5 day (ipp 2.8)
+
+ * add additional required metadata to output images
+ - WS : 2 day (ipp 2.8)
+
+ * add image lookup to detectability request 
+ - WS : 1 day (ipp 2.8)
+
+ * add weight / mask / cmf lookups to ps requests
+ - WS : 1 day (ipp 2.8)
+
+ * magic interface / release flags
+ - WS : 2 days (ipp 2.8)
+
+ * pending re-processing mode
+ - WS : 3 days (ipp 2.8)
+
+ * spec / re-design postage stamp web pages
+ - WS : 2 days (ipp 2.9)
+
+ * implement postage stamp web pages
+ - WS : 5 days (ipp 2.9)
+
+DVO
+
+ * validate Image / Object / Detection IDs
+ - EAM : 1 day (ipp 2.8)
+
+ * optimizations for Image / Object / Detection indexes
+ - EAM : 2 days (ipp 2.9)
+
+ * extend vectors to double and int types
+ - EAM : 0.5 day (ipp 2.9)
+
+ * convert time fields to unsigned int
+ - EAM : 0.5 day (ipp 2.9)
+
+ * function name cleanups
+ - EAM : 0.5 day (ipp 2.9)
+
+ * use partial loads for catalogs 
+ - EAM : 1 day (ipp 2.9)
+
+ * addstar -refcat -update mode
+ - EAM : 1 day (ipp 2.9)
+
+ * DVO replication tools
+ - EAM : 2 days (ipp 2.9)
+
+Output Tables
+
+ * generate PSPS P2 output tables
+ - WS : 2 days (ipp 2.9)
+
+ * generate PSPS Stack output tables
+ - WS : 2 days (ipp 2.9)
+
+ * generate PSPS Diff output tables
+ - WS : 2 days (ipp 2.9)
+
+ * generate PSPS output tarballs
+ - WS : 2 days (ipp 2.9)
+
+ * generate MOPS output tarballs
+ - PAP : 2 days (ipp 2.9)
+
+ * output CMF file documentation
+ - WS : 1 day
+
+IPP ORR Demonstration Analysis (post-camera refurb)
+
+ * Generate Starting Master Dark [full grid of darks vs temp & exptime]
+ - WHO : 2 days
+
+ * Generate Starting Master Flat [several nights of twilight flats]
+ - WHO : 2 days
+
+ * Manual Mask additions
+ - WHO : 3 days
+
+ * Generate Flat-field Correction [flat-field correction dithers for each filter]
+ - WHO : 3 days
+
+ * Demonstrate Photometric consistency [Stripe 82 / Stripe 10, second-pass dither]
+ - WHO : 3 days
+
+ * Demonstrate deep stack [MD example field]
+ - WHO : 3 days
+
+----------------------------------------------------------------------------------
+
+IPP Coding Milestones
+
+* ipp 2.7 -- 2008.08.15
+  * cleanup for all stages
+  * fix flat-field normalization bug
+  * update for all stages
+  * psastro measure zero point
+  * threading for pswarp, ppMerge, ppImage, ppStack, ppSub
+  * magic integration
+  *** EAM : 10.25d; PAP : 7d
+
+* ipp 2.8 -- 2008.08.29
+  * flat-field correction simtest suite
+  * psphot improvements
+  * fake source / forced photometry simtest suite
+  * detrend construction simtest suite
+  * pstamp ex. WWW
+  *** EAM : 6.5d; PAP : 4; WS 9d (no ipp 2.7 milestones)
+
+* ipp 2.9 -- 2008.
+  * pstamp WWW
+  * summit Q/A feedback
+  * PSPS output tables
+  * PSPS & MOPS output tarballs
+  * DVO updates
+  *** EAM : 15.5d; WS : 18d
+
+----------------------------------------------------------------------------------
+
+IPP GPC1 Pre-ORR Analysis Milestones
+
+* New Uncorrected Master Flat-field Images (using current best mask)
+  * ppMerge threading
+  * fix flat-field normalization bug
+  * 'validate' run with existing flats
+  *** possible concern: non-linearity of devices
+
+* Corrected Master Flat-field Images
+
+* Single-Image cell-to-cell background variation < 1%
+
+* Single-Image Photometric residuals < 2%
+
+* Single-Image Astrometric residuals < 20mas
+
+* Demo GPC1 Stacks (best-effort flats)
+
+* Clean GPC1 Stacks (minimal / no background residuals, PSF convolution applied)
+
+* Clean GPC1 Difference Image Set (< XXX false positive detections)
+
+* Demo GPC1 Magic Analysis (minimal quality inputs)
+
+* Clean GPC1 Magic Analysis (high quality inputs)
+
+----------------------------------------------------------------------------------
+
+Goals for the weeks of:
+
+07.27
+  EAM : ppMerge threading, ppImage threading, flat-field normalization bug, [finish demo science run]
+  PAP : ipp 2.6 release (07.30), finish magic scripts & tasks, output config files, [MOPS Megacam run 2a]
+  WS  : add'l output metadata, image lookup in det., weight, mask, cmf lookups, [monitor summit copy]
+  BG  : demo automatic (background) simtest
+
+08.03 : 
+  EAM : finish 'cleanup' for all stages; 'update' for chip stage, psastro zp [GPC1 detrend validate run]
+  PAP : ppStack threading, ppSub threading [MOPS Megacam run 2a]
+  WS  : magic interface issues, re-processing task, [monitor summit copy]
+ JHU  : flat-field correction simtest
+  BG  : set up cronjob for background simtest
+  JH  : documentation / bugzilla cleanup
+**MH  : psphot tests of crowded fields
+
+08.10 : 
+  EAM : 'update' for all stages, psphot threading [GPC1 improved flat-fields]
+  PAP : finish ppStack/ppSub threading & tests, ipp 2.7 release tarball (08.15) [skip release?]
+  WS  : PSPS P2 output tables, PSPS Stack output tables, [monitor summit copy]
+ JHU  : flat-field correction simtest / prepare for Megacam flatcorr demonstration 
+  BG  : design system to test simtest success / failure
+  JH  : documentation / bugzilla cleanup
+**MH  : psphot tests of crowded fields
+
+08.17 : 
+  EAM : psphot shakeout, detectability query [GPC1 flat-field correction run]
+  PAP : fake & forced simtest
+  WS  : (vacation)
+ JHU  : Megacam flatcorr demonstration 
+**MH  : psphot tests of crowded fields
+
+08.24 : 
+  EAM : more psphot shakeout, validate IDs -> DVO
+  PAP : ipp 2.8 release (08.29), [GPC1 Stacks]
+  WS  : (vacation)
+
+08.31
+  EAM : 2D color-correction in relphot, GPC1 Photometry validation
+  PAP : detrend construction simtest, [GPC1 Stacks]
+  WS  : PSPS Diff output tables, PSPS output tarballs, [monitor summit copy]
+
+09.07
+  EAM : DVO minor fixes, [GPC1 Photometry & Astrometry validation]
+  PAP : [GPC1 Stacks & Difference Images]
+  WS  : spec/design pstamp www, implement pstamp www
+
+09.14
+  EAM : extended source photometry [GPC1 Photometry & Astrometry validation]
+  PAP : [GPC1 Stacks & Difference Images + Magic Analysis]
+  WS  : continue with pstamp www
+
+09.21
+  EAM : DVO ID optimizations, DVO replication
+
+09.28
+  EAM : relphot outlier flagging, absphot
+
+10.05
+10.12
+10.19
+10.26
+11.02
+11.09
+11.16
+11.23
+11.30
+12.07
+12.14
+12.21
+12.28
+