    2222         Progress on mirror covers, but do not yet have it operational.
    2323         Lou inspected Dome.
    24 GPC2: Focal plane is nearly complete - one round of metrology has revealed one device that is stuck high. Will swap with neighboring device, and re-metrologize.
    25 Trying to get metrology done before Craig goes to review meeting.
     24GPC2: Focal plane is nearly complete - one round of metrology has revealed one device that is stuck high.
     25           Will swap with neighboring device, and re-metrologize.
     26           Trying to get metrology done before Craig goes to review meeting.
    2627
    2728Proposal:  working on with Gene and Richard.