  • GreatReprocessing

    v10 v11  
    1616== Great Reprocessing Order up to ~ Feb 1 ==
    1717
    18  * 3pi most recent complete 5 band region (stacking!!)
     18 * 3pi most recent complete 5 band region - RA 21 hours to 01 hours, have 4 images g,r,i, will have 4 images of z, and y after Dec 19.
     19 ** If we continue with this, have 4 or more images at sidereal rate, but from 01 hrs onward (trailing).
     20 ** In May start to get 6 images in z,y at 21 hours - can redo 21-01 hours over summer with 4 g,r,i and 6 z,y
     21 ** In End of Aug have 8 g,r,i and 6 z,y 
     22 ** Don't have 8 images complete until Nov 2011.
     23
    1924 * MD fields
    2025 * high resolution stack
    2126
    22 == GP after ~ Feb 1 ==
     27== GP End of January ==
    2328
    24  * 3pi stack of last  year + incoming - this will be 6 images / band over most of the sky, (4 in some places) and  8 in May and June, and then 8 from August 2011 onwards.
     29 * have demo month last year, plus completed 2 images z, y from Dec Jan this year. So only 2 images in 5 bands. - new catalog, stack?
    2530
    26  ** This is most important think to be ready
     31== GP End of February ==
    2732
    28  ** Need Quad processing worked out
     33 * 3pi stack of last  year + incoming
     34  ** completed observing 6 images in g,r,i - 4 from real time MDRM brick wall program + 2 last year demo month. Still only have two y,z images.
    2935
    30  ** What do we do with missed chunks?
     36  ** Middle of May, 4 images in y,z  over demo month region with 6 bands in g,r,i band
     37
     38 * Need Table of all this...
     39
     40== Quad Processing ==
     41
     42 * how to do for mops? note 1 pair on different tesselation from another pair.
     43
     44 * What do we do with missed chunks?
    3145
    3246 * all other incoming (MD, SS, until we reach at least March)
    3347
    34  * continue backwards with what ever cycles there are left
     48== summary ==
     49 * 4band completion from 21 hrs RA starting Nov 2010 at siderial rate
     50 * 8 band completion from 21 hrs RA strting Nov 2011
     51 * 4-6 bands in g,r,i, 2 to 4 bands y,z from 11.5 hours RA starting end of Feb
    3552
    3653