Great Reprocessing Order
- tasks for GP
*Gene's 1 message on tasks before GP
*Gene's 2 message on tasks before GP
Pre-GP re-reduction
- SAS -> PSPS
- MD04 -> PSPS
- M31
- STS
GP Reprocessing December through January
- All MD fields, 3pi at 4grizy from 21 hours onwards. Feed to PSPS.
Great Reprocessing Milestones
- Starting Nov 2010 have 4x g,r,i,z,y from 21 hrs RA moving at sidereal rate as we finish 4th z and y. Stack of 4 magiced. Have to do this to feed PSPS.
- End of Jan 2011 will have 2 x g,r,i,z,y from demo month - 11.5 hours RA to 15 hrs RA. Catalog for follow up science.
- From Feb 1 on, genuinely reprocessing old data and new data and stacking as we go. At this point turn off reprocessing of 4x stacks from 21 hrs.
- End of March 2011 will 6 x g,r,i and 2 * y,z over 11.5 hours to 15 hours RA. Start stacking of 6 gri (muggled?)
- End of June 15, 2011 will have 6x g,r,i, and 4 z,y over 11.5 hours to 15 hours RA. Start stacking of 6gri (muggled?), 4yz (magiced).
- End of Aug 2011 begin 8 x g,r,i and 6 x y,z at sidereal rate. Start stacking 8gri (muggled), 6yz(muggled?)
- End of Oct 2011 begin 8x g,r,i,z,y at sidereal rate. Start stacking 8grizy (muggled).
- End of Aug 2012 begin 12x g,r,i, 8 z,y
- End of Oct 2012 begin 12 g,r,i,z,y
- Begin Aug 2013 completed 12x g,r,i, 6 x z,y
- End of Sept 2013 have 12 x g,r,i,z,y and clean up observing. Can we create final stacks/catalogs as we go?
- Need PS1+PS2 consortium funding operations by Oct 1, 2013.
- Need funding to reprocess and serve PS1 Mission... 6 months of re-processing?
- Release of PS1 data to public domain May/April 2013.
- PS1SC Needs at least $1M more, maybe NASA comes up with half, need 2 -3 more partners to really cover the sky 3 times well. If no new funds, then 8 grizy...
Quad Processing
- how to do for mops? note 1 pair on different tessellation from another pair.
- What do we do with missed/delayed chunks?
Note: