| | 1 | This is Heather's DR2 timeline (to the best of Heather's knowledge, estimates for how long things will take) |
| | 2 | |
| | 3 | I have made a rough timeline for DR2 (more like an outline). The smallest unit of time in my timeline is 1 week, and I (arbitrarily) decided that Gene and I can be tasked on up to 3 tasks for DR2 at a time, Conrad gets 1 task at a time. Some tasks are clearly serial, (like, build, calibrate,test database), while others can be parallel (make P2 batches and test diff database). I created this mostly so I could have some guess as to how long things could take. |
| | 4 | |
| | 5 | Conrad's numbers are pulled from either asking him, or looking up how long things took for DR1. |
| | 6 | |
| | 7 | My numbers are estimated from either DR1 or other sources. There is overlap on different types of batches - this is because loading tapers off as a batch type nears completion, and it's possible to start up another batch type. I'm happy to fill available time (once dvo is calibrated) with loading whatever batches I can, but I do expect it to take quite a lot of weeks to make the batches. |
| | 8 | |
| | 9 | Gene's numbers are guesses (I am happy to correct as necessary) |
| | 10 | |
| | 11 | Not included is the testing/verification/investigations of ipptopsps/psps things, which is quite time consuming during loading, as well as all other Panstarrs related tasks. |
| | 12 | |
| | 13 | [[Image(Screen Shot 2017-04-12 at 9.19.28 PM.png)]] |