Heather's Tasks
Here is heather's list of tasks (related to IPP) to work on.
The most urgent (no particular order)
- u band stacks from MegaCam (more info here: http://svn.pan-starrs.ifa.hawaii.edu/trac/ipp/wiki/MeediumDeepUBand )
- multiple requests from KP5, JT, and ZZ.
- remaining issues
- we have clean/good processed single exposures from CADC
- astrometry is funny for some of it due to lack of stars
- possible ideas to fix:
- force to be linear fits in astrometry
- force to fit the exposure rather than the individual chips
- possible ideas to fix:
- chop out the crappy astrometry ones and stack
- isp/skyprobe
- Roger/Niall want skyprobe
- sort out dome occultations
- sort out bad focus
- astrometry/zeropoint problems (sorted - this has to do with how addstar was being run)
- does isp still not ingest properly RA/DEC/etc from fits file? yes...
- sort out skycells etc to make warps -- done!
- skycells command ran (with 5.57 arcsec/pixel, see here: http://svn.pan-starrs.ifa.hawaii.edu/trac/ipp/wiki/PS1_Tessellations )
- copied skycells to /local/ipp/isp/
- make stacks
- process SAS area of sky for testing - in progress! lots of stuff there...
- first attempt = {{{
chiptool -dbname isp -definebyquery -set_label sas.v0 -dateobs_begin 2010-01-01T00:00:00 -comment '%ps1%' -dateobs_end 2012-10-02T00:00:00 -set_workdir neb://@HOST@.0/isp/sas.v0 -ra_min 328 -ra_max 339 -decl_min -6 -decl_max 6 -set_end_stage warp -set_tess_id ISP.V0 -simple }}}
- note that ippMonitor lied and wasn't updated - dropped the 8 first attempts...
- psps
- spend this week verification of psps stuff
- further iterations of SASdvo -> ipptopsps -> psps
- will likely require changes to building dvos and ipptopsps
- extra = qf_perfect
- see http://ps1sc.ifa.hawaii.edu/PS1wiki/index.php/PSPS_heather for list of problems I know about (add others if necessary)
Lower priority Heather tasks
- ssp
- periodically download ssp from atrc (BAAAAD)
- work with jt to get monsta script and to process ssp (I have the scripts, need to automate them,etc)
- switch to datastore for grabbing files when ssp/uip computer gets sorted out
- when switched to datastore add ssp to summitcopy/registration
- uip - set that up as well (summitcopy/registration) - the uip machine is not ready yet
- gpc1 dvodbs
- continue building ThreePi?/LAP, backing up as necessary
- jtmd
- queue jtmd stuff as requested
- work on talks for ps1 seminar stuff