  • IPP_Current_Tasks

    v55 v56  
    1010a) Tasks required before the start of the survey:
    1111
    12  * IPP to OTIS interface : the code is in place; we will turn this on with basic rules by the end of this week (3/12 - CZW)
    13    * '''DONE''' : we now need to iterate with OTIS
     12 || IPP to OTIS interface || 3/12 - CZW || DONE || we now need to iterate with OTIS ||
     13
    1414 * Detectability Server : two items are required
    1515  * the program 'psphotDetect' must be finished (3/19 - EAM/CZW)