PS1 IPP Czar Logs for the week 2014.12.01 - 2014.12.07

(Up to PS1 IPP Czar Logs)

Monday : 2014.12.01

  • 09:53 Bill: restarted distribution pantasks which was sluggish with diff stage enabled. SAS distribution is all finished except for diff stage.
  • 13:00 Bill: ~ippsky is rerunning staticsky and skycal for sas.37
  • 17:00 MEH: setting up ippx049+ for ippsky staticsky/cal to use -- manually adding when ready, ~3x should be fine for 50G ram
    • ippx049--x088 have been setup and added temporarily to a x2 group (need split by pdu?), after Haydn's email x089-x092 also -- see x2 group for ones still down
  • 22:00 MEH: nightly processing not doing well w/ ippmd and ippsky running (or something else?) -- ipp083-087 overloaded/not responding and stalling registration

Tuesday : 2014.12.02

  • 07:11 Bill: started up fullforce in ~ippsky/staticsky (staticsky and skycal are finished except for one skycell that faulted with a data error. It is running now
  • 07:30 MEH: registration backed up quite a bit, too many nodes in use -- ippmd stop until nightly finishes
    • looks like something may have started ~0200, nightly rate dropped greatly then as well..
  • 08:30 MEH: taking some xNNN nodes out of ippsky until nightly finishes.. then probably could do 4x on those for FF
  • 08:40 MEH: an exposure (o6993g0619o) is stalled in registration.. been a while so restart summitcopy and registration (then stdsci once nightly is finished) -- had to manually run
    regtool -dbname gpc1 -revertprocessedexp -exp_id 829654
    
  • 09:30 MEH: ipp056,058,060 have space and could be moved out of repair to help ease load on new storage nodes and get nightly finished
    • same for ipp011,012,029,030
    • now get to see those load >50 -- so even when get 10G for ipp083-088 setup, the other 1G systems will get large loads?

Wednesday : 2014.12.03

Thursday : 2014.12.04

Friday : 2014.12.05

Saturday : 2014.12.06

  • planned downtime MRTC-B 590B Lipoa Automatic Transfer Switch (ATS) -- Saturday December 6th. They will be starting our shutdown processes at 9am and will hopefully start turning things back on at 3pm.
    • all processing stopped before ~8am
    • Haydn on site to start power down of systems @8am

Sunday : 2014.12.07